REPUBLIC OF THE PHILIPPINES
SOCIAL SECURITY SYSTEM
ENTERPRISE BACKUP PROJECT - SITE SURVEY FORM
DATA CENTER SITE SURVEY & INFRASTRUCTURE READINESS FORM
Scope: Site Code:
Site Name: Survey Date:
GPS Coordinates: Proposed Rack Location:
EQUIPMENT & HARDWARE DEPLOYMENT SCOPE (PER SITE)
Rack 1:
• 2x CE6885 TOR Switches (1U each)
• 1x OceanProtect X8000 (2U)
• 4x Backup Disk Enclosure (4U)
• 4x PDU2000-32-11/2-B1-3M
Rack 2:
• 2x Backup Servers - DP220 (2U each)
• 1x Veeam Hardening Server - DP220 (2U)
• 1x OceanProtect E8000 (2U)
• 4x Archiving Disk Enclosure (4U)
• 4x PDU2000-32-11/2-B1-3M
Item Criteria Description Requirement Standard & Technical Specs Status Remarks / Details
• 1. PHYSICAL & SPATIAL READINESS
1.1 Rack Space Availability Confirm required Rack Units (U) are available in each rack for new chassis and cable management.
1.2 Floor Weight Capacity Verify that raised floors and room foundations can support the cumulative weight of the racks and heavy storage units.
1.3 Access Route & Logistics Measure door frames, elevators, hallways, and turn radii from the loading dock to the data center to ensure equipment clearance.
1.4 Rack Depth & Mounting Check that existing rack depth and mounting rails accommodate deep enterprise storage enclosures and server chassis.
1.5 New Rack Location Check for possible new rack location considering rack dimension (2000 mm x 600 mm x 1200 mm) and front and rear clearance.
• Front Clearance: ≥ 1.0 meter
• Rear Clearance: ≥ 0.9-1.0 meter
• 2. ELECTRICAL & POWER INFRASTRUCTURE
2.1 PDU Input Voltage & Phase Confirm wall receptacles match the 220V Single-Phase requirement for the PDU2000-32-11/2-B1-3M units.
2.2 Receptacle & Plug Types Inspect wall outlets/receptacles (e.g., IEC 309 32A blue plug) to ensure compatibility with PDU input cables.
2.3 Circuit Breaker Capacity Verify dedicated circuit breakers (typically 32A or 40A per feed) support full rack loads with N+1 redundancy.
2.4 Feed A / Feed B Separation Confirm dual independent power feeds (UPS/Generator backed) are delivered to each rack for true dual-cord redundancy.
2.5 UPS Headroom Verify existing UPS units have sufficient kVA headroom to handle the total added active power load (~10.45 kW across two racks).
• 3. COOLING & ENVIRONMENTAL CONDITIONS
3.1 Net Cooling Capacity Confirm CRAC/CRAH units have sufficient net cooling output (~35,650 BTU/hr or 2.97 Tons additional capacity).
3.2 Airflow & Containment Verify front-to-back airflow patterns align with cold aisle / hot aisle layouts.
3.3 Existing Room Temperature Measure baseline room conditions / temperature and take note of existing ACU capacity.
• 4. NETWORK & CABLING
4.1 Upstream Uplinks Identify available core/aggregation switch ports (SFP+/QSFP) for Top-of-Rack (TOR) switch uplinks.
4.2 Fiber & Patch Panels Verify structured cabling paths, patch panel port availability, and cable tray space.
• 5. SAFETY & COMPLIANCE
5.1 Grounding & Bonding Verify availability of dedicated grounding tapping points/busbar positions (TMGB) for connecting new rack frame.
• 6. PHOTOGRAPHIC ATTACHMENTS & SITE EVIDENCE (PAGE 1)
📷 Click to upload Photo 1 (Existing Floor Layout) Existing Floor Layout
1. EXISTING FLOOR LAYOUT
📷 Click to upload Photo 2 (Photo of Proposed Location) Photo of Proposed Location
2. PHOTO OF PROPOSED LOCATION
• 6. PHOTOGRAPHIC ATTACHMENTS & SITE EVIDENCE (PAGE 2)
📷 Click to upload Photo 3 (Proposed Floor Layout) Proposed Floor Layout
3. PROPOSED FLOOR LAYOUT
📷 Click to upload Photo 4 (Equipment Layout) Equipment Layout
4. EQUIPMENT LAYOUT
• 6. PHOTOGRAPHIC ATTACHMENTS & SITE EVIDENCE (PAGE 3)
📷 Click to upload Photo 5 (Proposed Tapping Point & Cable Layout) Proposed Tapping Point and Cable Layout
5. PROPOSED TAPPING POINT & CABLE LAYOUT
📷 Click to upload Photo 6 (Proposed Grounding Tapping Point) Proposed Grounding Tapping Point
6. PROPOSED GROUNDING TAPPING POINT
• 6. PHOTOGRAPHIC ATTACHMENTS (PAGE 4) & SIGN-OFF
📷 Click to upload Photo 7 (Fiber Cable Layout) Fiber Cable Layout
7. FIBER CABLE LAYOUT
📷 Click to upload Photo 8 (Thermal / Cooling Heatmap) Thermal / Cooling Heatmap
8. THERMAL / COOLING HEATMAP
NOTED BY (SSS SITE COORDINATOR) PREPARED BY (IMPLEMENTATION CONTRACTOR)
Company: SOCIAL SECURITY SYSTEM
Personnel Name:
Designation:
Signature / Date:
Company: COMCLARK NETWORK & TECH CORP.
Name:
Designation:
Signature / Date: